Analysis Compiled 2 October 2026 Corrected 3 October 2026 read from the files themselves

Who wrote the Project Plan and why the September “minor amendment” is not minor

A Word file remembers who made it, who edited it, and who said what in its margins. The library system released the county’s Project Plan drafts as the original Word files, and they show who rewrote the plan in April: an editor signed in from the law firm Bracewell and IREN’s own people marked it up, county counsel pushed back, and the plan the committee recommended carried payment figures closer to IREN’s than to his, as an illustration and not a commitment. In September the “minor amendment” summary the committee was handed came from a Word file made at Ernst & Young, and it would give IREN the one thing county counsel had refused it in writing: activation without a vote of the Board.

Word files read
9
Margin comments
16
Tracked changes signed in from Bracewell
198
Illustrative floor at full build, V6
$36m
Illustrative floor at full build, recommended
$15m
Board vote to activate
removal proposed 29 Sep

Publication statement

Published by
Brian West
Author's position
IREN does not need our tax incentives to build and operate.
Status of the measure
Tabled by the Board of County Commissioners on 22 June 2026. Not adopted. No resolution number, adoption date, filing deadline or election date exists.
Basis
The Southeast Oklahoma Library System’s Open Records Act production of 2 October 2026, published in full and unaltered: the production note and every document, source [57] on the timeline, and letter 08 on the records register. Also the Kiamichi Technology Centers production ([55]) and the county’s posted minutes. No non-public information was received or relied upon.
How the files were read
A Word file is a zip of XML. The creator, last editor, dates, revision count and editing minutes are its document properties; tracked changes and comments carry their author and two times, the editor’s own clock and UTC; the editor list records the account each editor was signed in with. The site’s own code reads all of it from the published copies, so every name, count and time below can be checked by opening the same file. Nothing on this page was retyped from the files by hand except the quotations, and those were checked against them.
Who pays for this
Nobody. This site runs on a server the author pays for. No organisation funds the work and no one is paid to do it. Costs so far are a domain, server capacity, certified copies from the Secretary of State, postage, and the fees public bodies charge for records — $248.50 to date, itemised on the records page with the invoice or receipt behind every line. That figure will grow as the remaining 9 requests go out. If the funding position ever changes it will be said here.
Corrections
brian@mcalester.net · errors of fact will be corrected and the correction noted. If you are named on this page and something here is wrong, write and it will be fixed. This page was corrected on 3 October 2026: what changed.
01 / What a Word file remembers

What a Word file remembers

and why the county’s PDFs could not show this

Kiamichi Tech produced the same drafts as printouts. A printout shows the words. The original file shows the words and the hands: the library system sent the originals, as the request asked, and they carry five kinds of evidence.

  1. Document properties. Every Word file stores who created it, who last saved it, when each happened, how many times it has been saved (its revision number) and how many minutes it has been open for editing. These are written by Word itself, not typed by anyone.
  2. Tracked changes. With “Track Changes” on, every insertion and deletion is stored with the name of the person signed in and the time. A redline is simply these marks displayed. They are counted below as “marks”: one mark is one stretch of inserted or deleted text, or one inserted or deleted paragraph break or table row, so a mark can be a single digit, a whole paragraph or nothing but a line break. Of the 675 marks recorded against county counsel on 7 April, 174 are breaks and rows.
  3. Comments. Margin notes, each with its author, a time, and the exact words it is pinned to.
  4. The editor list. When an editor is signed in to Word with a work account, Word records that account beside the name on their changes and comments. It does so wherever the file is kept, so an account by itself does not show that a file was shared. Someone working in a copy kept in another organisation’s online workspace (SharePoint or OneDrive) is recorded differently, as a guest. The accounts are the strongest evidence on the page, because each is an email address the person was signed in with, not a display name anyone could type.
  5. Two clocks. Word stamps each comment, and since 2023 each tracked change, twice: once with the editor’s own clock and once in UTC. The gap between the two is what that computer’s clock was set to. It gives the exact time of a change, and it tells one editor’s machine from another’s.
02 / Who held the pen, in order

Who held the pen, in order

company lines are IREN and its advisers; county lines are counsel, the Clerk and the committee
The Project Plan from first draft to the “minor amendment”
DateWhoWhat the files and emails showSource
2 Mar 2026CommitteeThe committee’s agenda lists “Review of Draft Project Plan”. The draft in the library director’s file of meeting documents is headed “IREN Data Center Project” and watermarked “2/24/2026 Draft for Discussion Purposes Only”.agenda · draft · minutes
13 Mar 2026IRENMarat Ahmad of IREN leaves the first comment in the county’s working draft: “Note to County: discuss how this works.” It is still in the margin of the next draft the committee is sent, seventeen days later.V6 file
30 Mar 2026CounselDavid Floyd sends the committee Draft V6 with the EDA and TIA. The Board activates a district only “upon formal action of the County Commissioners”; the illustrative floor at 600 MW is $36 million a year. His cover email lists “No Public Reimbursement of Costs” as a safeguard.email
31 Mar 2026BracewellAn editor signed in as bucky.brannen@bracewell.com makes the first tracked changes, between 8:00 and 10:48 PM on a clock set to Central time: activation becomes automatic on the Company’s notice, the depreciation floor and the bar on tax protests are struck, and abatement may begin before the building is finished.V7 file
1–2 Apr 2026IREN · EYJason Date (signed in as jason.date@irisenergy.co) rewrites the activation thresholds and the payment table, cutting the floor to $7–11 million; Marat Ahmad adds “It’s important that this not be discretionary or require ‘formal action’ by the County Commissioners to begin tax abatement.” Evan Horn of Ernst & Young is recorded as a guest in a shared online copy; the one change against that account, at 7:07 PM Central on 1 April, puts a “~” before $25,000,000,000. The file is named “Project Plan Draft V7 (4.02.26) IREN Comments”.V7 file
3 Apr 2026CounselFloyd forwards “the most recent markup of the Project Plan that they sent me this morning” to the County Clerk and Chief Deputy, saying he will send back a version “eliminating anything I find objectionable.”email
6–7 Apr 2026CounselFloyd’s redline: 675 marks overnight, restoring “formal action of the County Commissioners” and an illustrative floor of $27.3–42 million. In the margin, to Ahmad: “Activation requires formal action by the County and notice to the Oklahoma Tax Commission. We can make it ministerial, but some formal action is required.” At 9:19 AM he sends it to Jason Date, Marat Ahmad and Evan Horn, and asks the Clerk to print copies for the meeting.V8 file · email
7 Apr 2026CommitteeThe committee meets. A motion to recommend the plan dies for lack of a second.minutes
8 Apr 2026CounselUnder “CONFIDENTIAL ATTORNEY WORK PRODUCT”: IREN’s floor rests on “a 60% discount value to the fair cash value assessed”; he would like “their depreciation around 40%.”email
20 Apr 2026CounselDraft V9. Formal action stays; IREN’s 50 MW trigger, one betterment payment and its right to walk away stay too, and counsel’s six-month outage allowance stands in place of the original 90 days. The illustrative floor at full build is $15 million: the plan calls its table “a non-binding example”, and counsel’s cover email says “This is not the final version of the payments … binding commitments will be in the Tax Incentive Agreement.”V9 file · email
21 Apr 2026CommitteeThe committee recommends V9, seven to none. The minutes are later certified “as this was the final meeting of the committee and no subsequent meeting will occur.”minutes
8 Jun 2026CounselAt the first public hearing: “Floyd explained that they cannot vote until after the 2nd public but there is no requirement that they have to vote then and that if they have to renegotiate the project plan it has to go through the whole process again.”minutes, p. 9
22 Jun 2026BoardThe Board tables the plan, 3–0, and sends it back to the committee. Nothing has been adopted.timeline
30 Jun 2026CounselTo the library director: closed-loop cooling “may show up as a minor amendment to the Project Plan as well when we reconvene.”email
25 Aug 2026Counsel“… because we consider the amendments to be ‘minor’ we don’t have to go back through the public hearing process.”email
29 Sep 2026Ernst & YoungEvan Horn’s file, company “EY”, saved at 20:52 UTC, summarises the amendment: “no further formal action is required on behalf of the County Commissioners.” At 4:02 PM Central, ten minutes later, the Clerk sends it to the committee as “a summary of the proposed changes to the project plan from Emerald.”Word file · email
30 Sep 2026CommitteeThe meeting’s handouts: the 21 April minutes, the agenda, the one-page summary, and a cease-and-desist from an impacted neighbouring landowner. The amended plan’s full text is not among them. What the committee did is not yet in any production.summary · letter
03 / The files

The files

every value read from the file by the site’s code

Times in this table are the document properties, which Word stores in UTC; Central time is five hours earlier from mid-March to early November and six in winter, when the two agreements were created. “Marks” are tracked changes, insertions and deletions, by the person they are recorded against.

Nine Word files from the library system’s production
FileWhoWhenTracked changesinserted / deletedCommentsAccounts recorded
Tax Incentive Agreement, Draft V2 Floyd & Driver, PLLC AdministrationcreatedDavid Floydlast saved 28 Jan 2026 19:59created30 Mar 2026 13:02last saved · 2,637 min editing · revision 89 none 0 none recorded
Project Plan, Draft V6 David FloydcreatedDavid Floydlast saved 27 Mar 2026 19:00created30 Mar 2026 13:02last saved · 53 min editing · revision 12 none 2 David Floyddavid@floyddriverpllc.comMarat Ahmadmarat.ahmad@iren.com
Economic Development Agreement, Draft V2 Jeff SabincreatedDavid Floydlast saved 26 Nov 2025 13:19created30 Mar 2026 13:02last saved · 3,911 min editing · revision 18 none 0 none recordediManage stamp IMANAGEOKC!65910660.1, sent from mcafeetaft.com
Project Plan, Draft V7 "(4.02.26) IREN Comments" Marat AhmadcreatedJason Datelast saved 2 Apr 2026 16:49created2 Apr 2026 23:34last saved · 23 min editing · revision 57 Jason Date 75 / 175
Brannen, Bucky 151 / 47
Marat Ahmad 3 / 2
evan.horn@ey.com 1 / 0
14 Brannen, Buckybucky.brannen@bracewell.comJason Datejason.date@irisenergy.coMarat Ahmadmarat.ahmad@iren.comDavid Floyddavid@floyddriverpllc.comevan.horn@ey.com guest
Project Plan, Draft V8 (clean) Marat AhmadcreatedDavid Floydlast saved 7 Apr 2026 14:17created7 Apr 2026 14:18last saved · 0 min editing · revision 3 none 7 Brannen, Buckybucky.brannen@bracewell.comDavid Floyddavid@floyddriverpllc.comMarat Ahmadmarat.ahmad@iren.comJason Datejason.date@irisenergy.co
Project Plan, Draft V8 (redline) Marat AhmadcreatedDavid Floydlast saved 7 Apr 2026 14:17created7 Apr 2026 14:17last saved · 0 min editing · revision 2 David Floyd 416 / 259
Brannen, Bucky 66 / 12
Jason Date 34 / 8
9 David Floyddavid@floyddriverpllc.comBrannen, Buckybucky.brannen@bracewell.comJason Datejason.date@irisenergy.coMarat Ahmadmarat.ahmad@iren.com
Project Plan, Draft V8 (redline), re-sent 8 Apr Marat AhmadcreatedDavid Floydlast saved 7 Apr 2026 14:17created8 Apr 2026 02:32last saved · 7 min editing · revision 1 David Floyd 416 / 259
Brannen, Bucky 66 / 12
Jason Date 34 / 8
9 David Floyddavid@floyddriverpllc.comBrannen, Buckybucky.brannen@bracewell.comJason Datejason.date@irisenergy.coMarat Ahmadmarat.ahmad@iren.com
Project Plan, Draft V9 (clean) Marat AhmadcreatedDavid Floydlast saved 20 Apr 2026 21:36created20 Apr 2026 21:38last saved · 2 min editing · revision 3 none 3 Marat Ahmadmarat.ahmad@iren.comJason Datejason.date@irisenergy.co
"Summary of Changes in Amended Project Plan" Evan HorncreatedEvan Hornlast saved 29 Sep 2026 20:52created29 Sep 2026 20:52last saved · 7 min editing · revision 2 none 0 company field: “EY”

Three things in that table worth slowing down for

“Created by” names whoever made the copy. The 2 April file is county counsel’s own V6 with the developer’s markup on it. Word gives every editing session of a document an identifier and keeps the list in the file, and all 1,753 of V6’s are in it. Its creator reads Marat Ahmad because the copy was made under that name; its creation time is 2 Apr 2026 16:49 UTC. When David Floyd then saved that file under new names, Word kept the creator, so Marat Ahmad appears as the creator of V8 and V9 without having written them. The useful fact is the lineage: the county’s draft went to the developer, came back as the developer’s file, and the plan the committee recommended was built in that copy.

Draft V6 is older than its date. It was created on 27 March but its last-printed date is 23 February, the day before the date on the first draft the committee was handed, so it was itself saved from an earlier file. The Economic Development Agreement was created on 26 November 2025 by “Jeff Sabin”, two weeks after the 12 November meeting that formed the committee; no account is recorded for that name and it appears nowhere else in the record. The file does carry a law firm’s document-management stamp: iManage document IMANAGEOKC!65910660.1, sent from an address at mcafeetaft.com, which is McAfee & Taft, and last modified there on 1 Dec 2025. The stamp says the agreement passed through that firm’s system. It does not say whom the firm acted for.

Zero editing minutes is not zero work. Floyd’s 7 April redline shows no editing time because it was saved from another copy; its 675 marks are dated from 6 April 23:56 to 7 April 09:17.

04 / The floor, draft by draft

The recommended plan’s floor sits near IREN’s ask, and binds nobody

the required payment at the top tier each draft defines

The “floor”, or required payment, is the least IREN would pay each year however low the abated tax came out. It is the number that protects the schools, the county, Kiamichi Tech, the health department and the library if the valuation disappoints. The drafts do not define the top tier identically, and they do not give their figures the same standing, so each bar is labelled with both. Only IREN’s table of 2 April is written as the payment itself. County counsel’s tables in V6 and V8 are headed “Illustrative”: they apply the abatement to an assumed value. V9 calls its table “a non-binding example”.

Required payment at full build, by draft

US$ millions a year · read from each draft’s Article III table, with the standing the draft gives it · March and April 2026

IREN’s ask, 2 Apr $11m $36m County counsel, V6 30 Mar 600 MW illustrative $11m IREN markup, V7 2 Apr 400+ MW the stated payment $32.4m County counsel, V8 7 Apr over 550 MW illustrative $15m Recommended, V9 20 Apr 550+ MW, stabilized non-binding example

V9 also lets the floor fall to $10–13 million a year for up to five years after activation, its “Introductory Period”, and it makes the payment owed in any year the greater of the minimum and the abated tax, so the minimum is what counts if the valuation comes in low. Its figures are not commitments. The plan says “Actual Minimum Required Payments … shall be set forth in the Tax Incentive Agreement”, and at the 21 April meeting, by the committee’s minutes, “Rhyne stated that the numbers in the documents are estimates. Floyd stated that they are illustrated to show what they framework is.”

The September summary does not mention the floor at all. Floyd’s own explanation of the gap, on 8 April, was depreciation: IREN’s floor was “significantly lower than what we proposed based on their depreciation assumptions”. Twelve days later the illustration in the plan he circulated had moved most of the way to IREN’s figure.

05 / What each hand changed

What each hand changed

quotations are the drafts’ own words; (Brannen), (Date) name the tracked change

Read across a row to follow one provision from county counsel’s draft, through the developer’s markup and counsel’s reply, to the plan the committee recommended and the September summary. Shaded cells are the September changes that run in the developer’s favour.

Fourteen provisions across five versions
Provision30 Mar · V6, county counsel2 Apr · V7, IREN markup7 Apr · V8, county counsel20 Apr · V9, recommended29 Sep · summary, EY
Who decides activation“The County Commissioners may, in their discretion, activate”; “activation shall occur only upon formal action of the County Commissioners”“shall be activated on the earlier of” … “the January 1 following written notice from the Company to the County electing to activate” (Brannen)“may be activated by formal action of the County Commissioners … in their reasonable discretion”as V8“no further formal action is required on behalf of the County Commissioners”
What triggers ita certificate of occupancy, 100 MW energized and $5 billion of assessed value50 MW and $1 billion of capital investment, “or will be achieved within the next twelve (12) months” (Date)50 MW reached or “the Company reasonably expects” it within twelve monthsas V8the earlier of evidence of substantial completion, the Company’s notice “that MW Energized has been achieved”, or “the tenth anniversary of the Project Plan Resolution”
Deadline“All Incentive Districts must be activated within ten (10) years”unchangedunchangedunchangedthe ten-year limit becomes an automatic activation date
Abatement before completionnot providedon the Company’s own statement of the MW it will reach, with the difference recaptured if it falls short (Brannen)on a good-faith estimate, trued up to actual MW each 1 Januaryas V8—
Abatement tiers0% under 100 MW; 50%; 70%; 85% at 400–600 MW40% under 100 MW; 60%; 80%; 85% at 400+ (Date)0% under 50 MW; 35%; 50%; 65%; 75%; 82.5%; 85% over 550as V8upper five tiers cut: 45%, 55%, 65%, 75%, 75% over 550
Floor at full buildillustrative $36,000,000 at 600 MW$11,000,000 at 400+ MW, as the payment itself (Date)illustrative $32,400,000 over 550 MWillustrative $15,000,000 stabilized, $10–13M introductory; “a non-binding example”not mentioned
Depreciationa “Deemed Business Personal Property Value” on a five-year refresh, “regardless of actual depreciation”; no reduction for “any protest, appeal, settlement”both struck; “General depreciation should be reflected in the assessed value” (Brannen)the deemed value and the bar on protests stay struck; equipment included “to the fullest extent permitted by applicable law”; value “determined independently by the County Assessor”; a County audit rightas V8—
Base valuetaxes on the site before activationassessed value as of 1 January 2026, certified by the assessor (Brannen)as V7, “fixed for the duration of the Term”as V8—
Outagesallowances up to 30 days; automatic reduction after 90struck (Brannen)six calendar months in a tax yearas V8—
Who the Company is“Emerald ProjectCo Inc.”“or any successors or assigns” (Brannen)“permitted successors or assigns”; an assignment needs the County’s approvalas V8adds any entity “majority-owned by, or affiliated with, or controlled by or under common control with Emerald ProjectCo Inc.”; keeps “permitted successors or assigns”; assignment “under procedures to be set out” elsewhere
Walking awaynot providedthe Company may terminate the Tax Incentive Agreement (Brannen)on 90 days’ notice; incentives end, past obligations stayas V8—
Betterment payment$100,000 to $3,000,000 a yearsame, on IREN’s tiers; “only one CBP” for both districts (Brannen)$100,000 to $5,000,000, adjusted for inflationstarts at $200,000$400,000 in 2027; paid to the Designated County Trust
MW Energizedcapacity “physically connected to the electrical grid”—metered, and verified by the County or its consultantas V8counts “on-site or ‘behind-the-fence’ generation”
Site“in the south of the County, near the town of Kiowa”“approximately two (2) miles south of the town of Kiowa along Highway 69” (Date)as V7as V7—

IREN’s April markup did not touch the definition of MW Energized; the September change to it is new, and it would let the developer’s own on-site generation, not only power delivered by the utility, earn the higher abatement tiers. IREN told the public in June it chose the site for “strong gas production”, and its own February questionnaire gives the fuel for its backup generators as “Diesel or natural gas (natural gas supply is available onsite …)” (supplement, p. 4).

06 / The margin comments

The margin comments

16 distinct comments; 3 still in the plan the committee recommended

Oldest first, by the UTC time Word stored with each comment. A comment carried from one draft into the next is listed once. Under each time is what the editor’s own clock read when it was written.

Every comment in the Project Plan files
When (UTC)AuthorCommentPinned toIn V9?
2026-03-13 19:5912:59 on a clock at UTC−7Marat Ahmad“Note to County: discuss how this works”Sectionyes
2026-03-19 16:1711:17 on a clock at UTC−5David Floyd“We’re going to need a more specific location than this.”in the south of the County, near the town of Kiowa.no
2026-04-01 01:4620:46 on a clock at UTC−5Brannen, Bucky“Concept is already included in the defined terms for “But-For Tax Liability” and “Required Payment,” but general depreciation should be reflected in the assessed value.”For purposes of calculating Required Payments and PILOT obligations, Business Personal Property shall be included in determining But-For...no
2026-04-01 01:5820:58 on a clock at UTC−5Brannen, Bucky““Project” is defined narrowly below to exclude the actual Data Center, so this Project Plan should refer to both the Project and Data Center in many instances.”Projectno
2026-04-01 02:2421:24 on a clock at UTC−5Brannen, Bucky“Addressed in Article 8.7 below”A Data Center or portion of the Project may be located within one or more Incentive Districts. In such event, the County Commissioners...no
2026-04-01 02:3821:38 on a clock at UTC−5Brannen, Bucky“General depreciation should be reflected in the assessed value.”depreciationno
2026-04-01 03:1022:10 on a clock at UTC−5Brannen, Bucky“Given the scope of investment, IREN should be entitled to begin abatement during construction (prior to Certificate of Occupancy) based on assurances that it will reach a stated MW Energized.”If an Incentive District is activated based on written notice from the Company (prior to Certificate of Occupancy), such written notice...no
2026-04-01 03:1522:15 on a clock at UTC−5Brannen, Bucky“Given the scale of the facility, “reasonable allowances” should be afforded even if retooling or repairing the facility takes longer than 90 days.”or maintenance not exceeding thirty (30) days. Failure to maintain MW Energized thresholds for more than ninety (90) days shall result...no
2026-04-01 20:1213:12 on a clock at UTC−7Marat Ahmad“Note to County: Is this intended to be an average? First year following activation, or some other year range?”Estimated But-Forno
2026-04-02 16:5009:50 on a clock at UTC−7Marat Ahmad“Updated for consideration”in the south of the County, near the town of Kiowa.no
2026-04-02 16:5309:53 on a clock at UTC−7Marat Ahmad“Note to County: It’s important that this not be discretionary or require “formal action” by the County Commissioners to begin tax abatement. IREN must be able to rely on the tax abatements when making its decision to invest.IREN proposes that we can elect to activate the incentive district before energization if energization is occurring in the next 12 months. IREN propose revised conditions of minimum 50MWs and $1B investment per phase, which is still a meaningful investment for IRENs business and the County.”Section 8.2: Establishment of Incentive District No. 1. This Project Plan establishes Incentive District No. 1. The County Commissioners...no
2026-04-02 16:5509:55 on a clock at UTC−7Marat Ahmad“Note to County: This should be based on capital investment and not assessed value.”valuecapital investmentno
2026-04-02 18:0511:05 on a clock at UTC−7Jason Date“Note to County - what do you need for this exhibit?”Exhibit “C”: Existing Uses and Conditionsyes
2026-04-02 18:0511:05 on a clock at UTC−7Jason Date“Note to County - what do you need for this exhibit?”Exhibit "D”: Proposed Improvements and Usesyes
2026-04-07 05:0200:02 on a clock at UTC−5David Floyd“I agree. I think a cleaner fix would be the revised definition of “Project” which includes the actual Data Centers”Projectno
2026-04-07 05:3600:36 on a clock at UTC−5David Floyd“Activation requires formal action by the County and notice to the Oklahoma Tax Commission. We can make it ministerial, but some formal action is required.”Section 8.2: Establishment of Incentive District No. 1. This Project Plan establishes Incentive District No. 1. Incentive District 1 may...no
What each editor’s clock was set to, from the two stamps
EditorClockWhich is
Jason DateUTC−7US Pacific daylight time
Marat AhmadUTC−7, UTCUS Pacific daylight time; already UTC, which is consistent with Word used in a web browser
Brannen, BuckyUTC−5US Central daylight time
David FloydUTC−5US Central daylight time
evan.horn@ey.comUTCalready UTC, which is consistent with Word used in a web browser

A clock is how a computer was set, not proof of where anyone sat. What the clocks add is the order of work and the kind of machine. The tracked changes recorded against Brannen, Bucky are the only ones in the markup with no UTC stamp, which is what a copy of Word from before 2023 would write; the comments from the same sitting carry one, five hours behind UTC. The change recorded against Evan Horn’s guest account, and some of Marat Ahmad’s, are stamped in UTC already, which is consistent with Word used in a web browser on a shared copy, and the earliest of those came some twenty hours after the Bracewell account’s last change. So the markup was not all made in one sitting or on one kind of machine: the Bracewell account’s changes came first, on a clock set to Central time, and the first sign of the shared online copy comes after them.

Exhibits C and D, “Existing Uses and Conditions” and “Proposed Improvements and Uses”, were still title lines with nothing under them in the plan the committee recommended, with IREN’s question to the county, “what do you need for this exhibit?”, still pinned to each. 62 O.S. § 858(A)(5) requires both.

07 / The “minor amendment”, against the plan’s own test

Not minor, by the plan’s own test

which is also the statute’s, and on county counsel’s own earlier words

The plan sets its own test for a minor amendment, in Section 9.6 of the version the committee recommended:

“The County reserves the right to approve minor amendments to the Project Plan, as provided in the 62 O.S. § 858(D), where desirable and appropriate to implement and achieve the objectives of this Project Plan, as long as any such amendment does not change the character or purpose of the plan. These minor amendments include adding to the area of any Incentive District, so long as the additions, considered on a cumulative basis during the twenty-five (25) year term of each Incentive District, do not exceed five (5) percent of the area of the Incentive District.”

Project Plan V9, Section 9.6 · Word file

The test is not only the plan’s. It is the statute’s own definition, 62 O.S. § 858(D): “An amendment is considered to be minor if such amendment does not change the character or purpose of the plan; does not add more than five percent (5%) to the district’s area; or does not add more than five percent (5%) to the public costs of the plan to be financed by apportioned tax increments.” The statute joins its three conditions with “or”, and the county may argue that meeting any one of them is enough. Section 9.6 does not read that way: it allows a minor amendment only “as long as” the character and purpose of the plan are left alone.

Measured against that, the September summary would change four things a twenty-five-year abatement is built on:

1. Who turns it on

From “formal action of the County Commissioners” to automatic: on evidence of substantial completion, on the Company’s notice that the megawatts have been reached, or at the tenth anniversary with nobody acting at all. County counsel refused exactly this in April: “some formal action is required.”

2. What earns the top tiers

On-site “behind-the-fence” generation would count toward MW Energized the same as power from the grid, so the developer’s own plant could carry it up the abatement ladder.

3. Who gets the incentive

“Company” would widen to any entity majority-owned by, affiliated with or under common control with Emerald ProjectCo. Section 9.7, which now lets nothing be assigned without the County’s review and approval, would be amended “to allow for assignment … under procedures to be set out” elsewhere; the summary does not say whether that approval survives. The plan would no longer fix who holds a twenty-five-year tax benefit.

4. The money

Every tier above 150 MW would be cut, and the 2027 betterment payment would double to $400,000. These help the taxing entities, but they rewrite the deal’s central numbers just the same.

There is also a step before the test. No plan has been adopted. The Board tabled it on 22 June. Under 62 O.S. § 858(D), “The governing body may grant the department, agency or public entity in charge of the implementation of the project plan the authority to make minor amendments to the plan”: a power over an adopted plan, granted by the Board. Under § 858(C), before an amendment is adopted “the governing body shall give notice concerning such amendment and hold public hearings on such amendment in the manner prescribed by Section 859 of this title.”

County counsel said as much in public. On 8 June, by the county’s own minutes, he told the hearing that “if they have to renegotiate the project plan it has to go through the whole process again.” By 30 June he was describing a change as something that “may show up as a minor amendment”; by 25 August, “because we consider the amendments to be ‘minor’ we don’t have to go back through the public hearing process.”

That is a reading of the documents, not a ruling. Whether an amendment is minor is, in the end, for a court if anyone takes it to one. What the documents settle is narrower and harder to argue with: the label was in use by 30 June, for a closed-loop cooling clause, and by 25 August it covered “the amendments” as a whole, before the committee saw a word of them; and the change at the centre of it is one the county’s own counsel had said in writing could not be made.

08 / The cease-and-desist

The cease-and-desist: right on the law, two slips

hand-delivered for the record at the 30 September meeting

An impacted neighbouring landowner handed the committee a “Formal Cease-and-Desist Notice and Demand for Statutory Compliance” at the 30 September meeting, and Ron Durbin of Guerrilla Publishing had written to the Board and every member the night before. Both make the same three points, and the documents above support all three:

  1. There was nothing to amend. The plan was tabled, not adopted, and minor-amendment power is a power over an adopted plan, granted by the Board.
  2. These changes are not minor. Section 9.6’s own test is “character or purpose”, and section 07 above sets out four changes that go to both.
  3. Changes to the plan go back through notice and two hearings. That is § 858(C), and it is what county counsel told the public on 8 June.

The landowner’s letter has two errors the county could use to wave it away, so they are worth knowing:

  • It cites “62 O.S. §859(D)” for minor amendments. The provision is § 858(D).
  • It says Section 9.6 “limits minor amendments exclusively to boundary adjustments not exceeding five percent.” It does not: 9.6 says minor amendments “include” such additions, which is an example, not the whole list. The argument does not need that claim. 9.6’s “character or purpose” test does the work by itself.

Durbin’s letter cites the 8 June minutes “at 9”, and that is right: it is the minutes’ own page number. The passage is the eleventh page of the county’s posted file only because two agenda pages come first. From their second page on, the minutes carry a running header dated “June 1, 2026”; their first page, both agendas and the county’s file name say 8 June. On the amendment, nothing else in either letter is contradicted by the files.

09 / Terms used on this page

Terms used on this page

in plain words, as the plan uses them
Incentive district; activation
The plan draws two districts over IREN’s ground. Nothing is abated until a district is activated, which starts its twenty-five-year clock. Who decides when that happens is the question this page turns on.
Abatement and its tiers
The share of the new property tax IREN does not pay. It rises with the megawatts in service: in the recommended plan, 0% below 50 MW up to 85% above 550 MW.
MW Energized
The megawatts actually powering the data center, which set the tier. The original definition counted capacity “physically connected to the electrical grid”; the September summary would count IREN’s own on-site generation too.
Required payment, or floor
The least IREN pays in a year, whatever the abated tax comes to. It protects the taxing entities if the valuation disappoints. The “Introductory Period” lets it be lower for up to five years after activation. In the recommended plan it is the greater of a minimum and the abated tax, and the minimums printed there are illustrations: the binding figures are left to the Tax Incentive Agreement.
But-for tax; depreciation
The tax that would be due with no abatement at all. Servers lose taxable value quickly as they age, so how depreciation is counted decides how fast that number, and anything tied to it, falls. The “Deemed Business Personal Property Value” IREN’s markup struck out assumed the equipment is refreshed every five years, which held the value up.
Base value
The taxable value of the ground before the project. Only value above it is abated.
PILOT
A payment in lieu of taxes: what IREN pays on top of its actual tax bill to bring the total up to the floor.
Community betterment payment
A separate yearly payment from IREN, outside the property-tax system, now to be paid to a county public trust.
Behind-the-fence generation
Power generated on the site for the site’s own use, rather than bought from the utility over the grid.
Assignment; “common control”
Assignment is handing the plan’s rights to another company. “Under common control” reaches any company owned by the same parent, so the September wording would let the benefit move within IREN’s group, and to successors, under procedures not yet written.
Minor amendment
A change to an adopted plan that the Board has delegated authority to approve without new hearings, under 62 O.S. § 858(D), and that by the statute and by the plan’s own terms does not “change the character or purpose of the plan.”
10 / What this does not prove

What this does not prove

  1. That Brannen acted for IREN. The file records an editor signed in as bucky.brannen@bracewell.com. That this editor was acting for IREN is a reading of the file, not a statement in it: the changes sit in the file named “IREN Comments” and argue IREN’s position. Nobody has said so in writing yet.
  2. Whose workspace it was. Evan Horn is recorded as a guest, which means a shared online copy was hosted by an organisation other than Ernst & Young. Marat Ahmad and Jason Date are recorded without the guest marker, and the 2 April file was made under Ahmad’s name, which points to IREN’s own workspace. The file does not name the host, and nothing in it places the Bracewell account in that shared copy: see section 06.
  3. Where anyone sat. The files give exact times and what each editor’s clock was set to. A clock setting is not a location.
  4. Who “Jeff Sabin” is, who created the first Economic Development Agreement, and whom McAfee & Taft acted for when that file passed through its system.
  5. Who chose the summary’s words. The September file was created and last saved under the name Evan Horn, in a copy of Word registered to “EY”. That shows where the file was made, not who decided what it should say.
  6. What the committee did on 30 September. Its minutes are not yet in any production, and the full text of the amended plan has not been produced by anyone.
  7. Anything about anyone’s motives. A developer’s lawyers and consultants marking up a draft in the developer’s favour is ordinary. What the files show is whose words became the county’s, and that is a matter of record, not of intent. Nobody named here is accused of anything.
11 / Sources

Sources

  1. [1]

    Southeast Oklahoma Library System — Open Records Act production, 2 October 2026

    186 files, 67 distinct, produced free of charge in answer to letter 08 · every file published byte for byte · the production note, the redaction statement and the full list are source [57] on the timeline

    The nine Word files in section 03, their properties, tracked changes, comments and editor lists; the first draft of 24 February and the 2 March agenda; the developer’s answers to the questionnaire’s data center supplement; counsel’s emails of 30 March, 3 and 7 April, 8 April, 20 April and 30 June; the Clerk’s email of 29 September; the 21 April minutes as certified; the 30 September handouts, including the summary and the cease-and-desist.

    timeline → source [57], the production note · records register → letter 08

  2. [2]

    Kiamichi Technology Centers — Open Records Act production, 18 September 2026

    Source [55] on the timeline

    Counsel’s email of 25 August 2026 on “minor” amendments and no further hearing.

    the email · timeline → source [55]

  3. [3]

    Board of County Commissioners — minutes of the special meeting and public hearing, 8 June 2026, Southeast Expo Center

    11 pp.: two agendas and nine numbered pages of minutes, posted by the county without a text layer; read by optical character recognition and checked against the page image. Pages 2 to 9 of the minutes carry a running header dated “June 1, 2026”

    Page 9 of the minutes, the eleventh page of the file: “if they have to renegotiate the project plan it has to go through the whole process again.” Page 3: “strong gas production”.

    minutes (copy) · county original

  4. [4]

    62 O.S. § 858 — Local Development Act, project plans and amendments

    Oklahoma State Courts Network, retrieved 25 September 2026

    § 858(C) on notice and hearings for amendments; § 858(D) on delegated minor amendments and what makes an amendment minor; § 858(A)(5) on the required exhibits.

    oscn.net → 62 O.S. § 858

12 / Corrections

Corrections

3 October 2026, the day after publication

This page was checked again against the files the day after it went up. These things were wrong, or said more than the files do. Each has been changed above.

  1. The committee had seen a draft. The page said that when IREN’s first comment was made on 13 March “the committee has not yet been sent a draft.” The committee’s 2 March agenda lists “Review of Draft Project Plan”, and a first draft dated 24 February is among its meeting documents. The comment was made in the county’s working file between that draft and the next.
  2. Ron Durbin’s page citation was right. The page said his letter cited page 9 of the 8 June minutes where the passage is on page 11. Page 9 is the minutes’ own number; it is the eleventh page of the county’s file only because two agenda pages come first. The error was this page’s, not his.
  3. The times can be known. The page said the exact times of the margin comments could not be proven. Word stores a UTC time beside each one, and beside most tracked changes, and the times here now use them. That moves the one change recorded against Evan Horn from 2 April to the evening of 1 April, and the page now says what that change was: a single character.
  4. Whose workspace. The page said the plan was rewritten “inside the developer’s own shared workspace”. The files show a shared online copy in which Horn was an outside guest, and they point to IREN as its host, but they do not name the host, and nothing places the Bracewell account in that copy. The opening paragraph and sections 01, 06 and 10 now say so.
  5. The floor figures are illustrations. The page marked only the first of the county’s figures as illustrative and said the floor in the recommended plan “is $15 million”. All three of the county’s tables are headed as illustrations, and the recommended plan calls its own “a non-binding example”. The chart and the text now give each figure the standing its draft gives it.
  6. Three attributions. The six-month outage allowance is county counsel’s wording, not IREN’s. The recommended plan already allowed assignment with the County’s approval, so the September summary would not make the plan assignable for the first time, and the summary keeps the word “permitted” before “successors or assigns”, which this page had dropped. IREN’s questionnaire gives “Diesel or natural gas” for its backup generators, not natural gas alone.
  7. Smaller things. The provisions table has fourteen rows, not thirteen. “Created by” is not always inherited: the 2 April file is a copy of county counsel’s V6 and names Marat Ahmad as its creator. A “mark” can be a paragraph break or a table row as well as words. Central time in winter is six hours behind UTC, not five. Three quotations had been cut short or re-capitalised and are now given as written. The September summary is a proposal, and the page now says “would” where it said “gives” and “removed”.

Two things were added that the first reading missed: the document-management stamp inside the Economic Development Agreement file (section 03), and that “character or purpose” is the statute’s test as well as the plan’s (section 07). The timeline said the September summary “makes the plan assignable”; that row was corrected the same day.

The one-page version